29.06.2011

GEO ALLIANCE completes installation of Propak refrigeration system

GEO ALLIANCE has successfully completed installation of Propak (Canada) refrigeration system on Lutsenkivske gas processing plant.

16.05.2011

GEO ALLIANCE starts the preparation of drilling site for well #1 Bokhanivske

The soil on the drilling site is removed, temporary road construction is about to start. Contract for drilling is being negotiated with the contractor. The well depth is projected to reach 5150 m.

04.03.2011

GEO ALLIANCE starts drilling of well #15 Lutsenkivske

The well is expected to be launched in the 1st quarter of 2012. The well depth is projected to reach 5950 m.

12.07.2010

Electric submersible pump (ESP) installed in well #2 Berestivske

An electric submersible pump (ESP) is being installed in well #2 Berestivske in order to boost oil production. As a result oil production is expected to increase 2-2,5 times.

12.07.2010

1st-stage reconstruction of Lutsenkivske gas processing plant (GPP) successfully completed

GEO ALLIANCE completes the first stage of reconstruction at its Lutsenkivske gas processing plant (GPP).

02.07.2010

GEO ALLIANCE boosts natural gas production 13% in January-June 2010 compared to the same period in 2009

In January-June 2010 GEO ALLIANCE produced 66 355 thousand m3 of gas, 13% more than in the same period of 2009 (58 797 thousand m3).

24.06.2010

Drilling on schedule for well #11 Lutsenkivske

Drilling on well #11 Lutsenkivske is progressing on schedule. Casing setting is planned for July. The delivery of the well is expected in October 2010.

23.06.2010

Schlumberger and Halliburton successfully complete work on well #11 Lutsenkivske

GEO ALLIANCE has contracted Schlumberger to perform borehole geophysical surveys and Halliburton for cementing works on well #11 Lutsenkivske. The works have been successfully completed.

17.06.2010

Tender for well design on wells #15 Lutsenkivske and #1 Bokhanivske completed

GEO ALLIANCE awards the contract for well design on wells #15 Lutsenkivske and #1 Bokhanivske to OOO “NPO Naftogazproekt”.

02.06.2010

The Group receives the permit for commercial production for Makartsivske field

The Group receives the permit for commercial production for Makartsivske field.